Installing imos iX 2025 step by step: preparing with IT, the installation itself and the checks afterwards, including comparing CNC programs.

Short answer: Prepare the installation with your IT administrator (permissions, shared folder, firewall, backup), install as administrator from the C drive and don't simply copy your old imos.ini. Finishing the setup is not the end: check the database, paths, drawing settings and licence, and compare the CNC output of a reference order between the old and the new version.

Information

Applies to

  • imos iX 2025 (the procedure is largely the same as for imos iX 2023)
  • iX CAD on AutoCAD (full or OEM version), CAM iX, database on Microsoft SQL Server (Express or Standard)
  • Optional integrations, such as Proteus
  • Last reviewed: October 2026

The video below walks you through the installation of imos iX 2025 step by step.

Video

Installing imos iX 2025

Step by step: installing imos iX 2025 (video in Dutch).

Installing imos iX 2025

Preparation

  1. Check that the workstations meet the system requirements (CPU, memory, SSD, graphics card).
  2. Ask your IT administrator in advance for temporary administrator rights on the workstations and Remote Desktop access to the server.
  3. Have a shared folder set up on the server, for example \\SRV-FILE\imos, with read and write access for all imos users.
  4. Have that folder mapped as a network drive on every PC, preferably I:\.
  5. Agree that incoming traffic to SQL Server is allowed through the firewall (default TCP port 1433).
  6. Check that both the database and the imos folder (I:\) are included in the backup.
  7. Check the database size. SQL Server Express is limited to 10 GB.
  8. Optionally run a defragmentation via the Organizer.
  9. Pick a reference order and keep the CNC programs the current version generates for it.
  10. Copy the installation files to C:\Temp on each PC.

Installation

  1. Using the full version of AutoCAD? Start AutoCAD once as administrator first, then close it.
  2. Start the imos setup from C:\Temp via right-click Run as administrator.
  3. On the first PC, run the database check for the new version.
  4. Start from a clean imos.ini for version 2025 and compare it line by line with your old imos.ini. Only carry over deliberate changes.
  5. Enable the connector collision check with COLLISION_CHECK_CONNECTORS=2.
  6. Make sure all folders in the configuration point to the network drive (I:\), not to a local path.
  7. Run Reset screens (Reset schermen in the Dutch interface).

Settings after installation

  1. Dock the command line and check the right-click settings.
  2. Check that AutoSave and snap points are switched on.
  3. Set up the ViewCube for quick view changes.
  4. Assign the graphics card and set the Windows graphics preference for imos/AutoCAD to high performance.
  5. Set the background of the realistic visual style to white.
  6. Copy the drawing template (IMOS.dwt) from the central folder to %appdata%\imos AG\imos AG\iX CAD 2025\config.
  7. Check the template: default scale 1:20 and the imos dimension styles (such as IMOS_DIM_BLUE) present.
  8. Create a front view, top view and section, and link the default dimensioning and annotations.
  9. Under Batch Plot, switch off the warning with Do not show me this warning again.
  10. Missing .ctb files? Add the path C:\Program Files\imos AG\iX CAD 2025\BIN\Plotters\Plot Styles in the AutoCAD options.
  11. Configure the columns in the Variables command and the article-specific variables.
  12. Set up barcodes and reports in imos itself wherever possible, not through the imos.ini.
  13. Check the Visu-manager, the connector scan (do the images load?) and any integrations such as Proteus.
  14. Check the CNC generation checkboxes and workflows.
  15. Set the number of threads for CAM generation based on the slowest PC in the company. Round down and test.
  16. Log in to the database with a personal user with superuser rights. Keep the default admin account for administration only.

Final check and clean-up

  1. Open an existing order.
  2. Test automatic views and dimensioning.
  3. Generate the CNC programs for the reference order and compare them with the output of the previous version.
  4. Run a test plot.
  5. Only uninstall the version before the previous one, so you can still roll back.
  6. Install the AutoCAD material library if needed (start a render and AutoCAD offers the download) and remove old libraries.
Tip

As a rough guide, allow about 1 hour for the first PC and about 30 minutes for each additional PC. A server migration takes about 1 hour on top. Send your IT administrator a short email in advance listing what you need; it saves waiting time on the day.

Why this approach?

Running the setup is the easy part. In practice, we often see settings skipped after a standard installation: paths pointing to a local drive instead of the network drive, missing .ctb files or dimension styles, or an old imos.ini lacking new parameters. You only notice weeks later, in a drawing or a CNC program.

That is why we work with a fixed protocol of more than 25 checkpoints. The most important one is the CNC output comparison: a reference order that produces the same programs in the old and the new version gives certainty before anything goes into production. The number of CAM threads is matched to the slowest PC because the setting applies to everyone. And keeping an older version installed gives you a fallback.

Backup and permissions are part of the job. Separate backups and limited permissions make you less vulnerable to ransomware. Agree on this with your IT administrator, who remains responsible for the backup itself.

Tip

Don't start with an empty database. After installation imos iX runs, but without a library you can't draw yet. With Wood Intelligence Plus you put the Wood Intelligence database into your test database as a blueprint: a filled imos iX database with connectors, hardware, handle concepts, example cabinets, materials and edge banding. That way you test the new installation straight away with working cabinets. Read how to approach this in Planning an imos iX implementation, or read more about Wood Intelligence Plus.

Frequently asked questions

Can I install imos iX 2025 alongside my current version?

Yes. We deliberately keep the previous version and only remove the one before it. That way you can roll back if a problem turns up after the installation.

Why does a licence message appear after installation?

That is normal after an update. Approval runs automatically under your maintenance contract and the message then disappears by itself. If it stays for more than a few working days, get in touch; there is probably a licence issue.

How long does an installation take?

As a rough guide, about 1 hour for the first PC and about 30 minutes for each additional PC. If the database also moves to a new server, allow about 1 hour extra.

What does my IT administrator need to prepare?

Temporary administrator rights, Remote Desktop access to the server, a shared imos folder with read and write access and a fixed drive mapping, a firewall rule for SQL Server (default TCP 1433) and agreements on backing up the database and the imos folder.

Further reading

More than one solution

Almost every question in this knowledge base has more than one solution. The best fit depends on your workflow, machinery and integrations. Not sure which applies to you, or are you using software we don't (yet) support? Feel free to email Wood Intelligence. We're happy to think along with any challenge.

imos is a trademark of imos AG. Wood Intelligence is an independent consultancy.

Download access

Sign in to check whether this download is available.